Project Update: Erisha Smart Manufacturing Hub at RAKEZ, Ras Al Khaimah
Transparency, accountability, and strict adherence to project timelines are the cornerstones of world-class infrastructure development.
To keep our stakeholders, partners, and the wider industry accurately informed, Rana Exim FZ-LLC("Employer") is issuing an official update regarding the Erisha Smart Manufacturing Hub at RAKEZ, Ras Al Khaimah.
Following a comprehensive compliance review and repeated site inspections, Rana Exim FZ-LLC issued a formal Notice of Termination on 25 September 2026 to GHV Infra FZ-LLC ("Contractor")—a wholly owned subsidiary of GHV Infra Projects Limited—terminating the EPC Agreement dated 6 October 2025. Furthermore, Rana Exim has forfeited the Contractor's Earnest Money Deposit (EMD) following their failure to mobilise the site even after more than 12 months from the project award.
While misleading disclosures have been submitted to the BSE attempting to deflect responsibility, the factual record demonstrates that termination was necessitated by multiple material breaches and contractual defaults by the Contractor:
🔹 Delayed Financial Securities: Failure to submit the Earnest Money Deposit (EMD) within the stipulated 45-day timeframe (completed 221 days past the contractual deadline), alongside significant delays in furnishing required Corporate Guarantees as Performance Security.
🔹 Failure to Achieve Initial Mobilisation: Failure to mobilise and commence preparatory site activities within the 90-day Mobilisation Period—and well beyond the 120-day immediate termination threshold—following the Letter of Award.
🔹 Wrongful & Unauthorised Suspension: Issuing an unsubstantiated suspension notice on 10 September 2026 without contractual entitlement, which was formally rejected by the Employer.
🔹 Non-Compliance with Notice to Resume: Disregarding the Employer’s formal directive to reinstate resources and resume full operations by the 19 September 2026 deadline.
🔹 Obstruction of Site Access: Locking site access gates and restricting the Employer from entering or assuming control of the property, as verified during multiple site inspections between 12 September and 19 September 2026.
Moving Forward
Rana Exim FZ-LLC remains steadfast in its commitment to the timely delivery, operational excellence, and highest international standards of the Erisha Smart Manufacturing Hub. We are actively advancing our execution roadmap with partners who share our dedication to integrity and performance, ensuring this landmark industrial project at RAKEZ achieves its full vision.